Small Residential One to Two Days
Small pipe insulation removal or a bathroom floor tile area: one to two days including containment, removal, and waste disposal.
Medium Projects Three to Five Days
Popcorn ceiling removal in multiple rooms or substantial pipe insulation: three to five days.
Large Commercial One to Four Weeks
Full building abatement before demolition: one to four weeks depending on building size and total quantity of ACM.
Regulatory Lead Time
NESHAP requires 10 business days notice before commercial demolition involving regulated asbestos quantities. Plan your project timeline accordingly.
Post-Abatement Clearance
Clearance air testing adds approximately 24 hours after abatement is complete. Containment cannot be removed until clearance is achieved.